Getter Pool Construction by Martin Pools
PRODUCTION DAY 1 - 1/10/2019
PRODUCTION DAY 2 - 1/11/2019
PRODUCTION DAY 3 - 1/14/2019
PRODUCTION DAY 4 - 1/15/2019
INSPECTION DAY 5 - 1/16/2019: Steel and Ground Inspection - Passed
PRODUCTION DAY 6 - 1/21/2019
PRODUCTION DAY 7 - 1/22/2019: GUNITE
1/24/2019: INVOICE 22181 PAID; STRIP AND BACKFILL PHASE NEXT
PRODUCTION DAY 8 - 1/26/2019: Lumber stripped out in preparation for backfill.
PRODUCTION DAY 9 - 1/31/2019: Soil filled in and tamped down. Ground around pool leveled to grade and excess dirt removed.
PRODUCTION DAY 10 - 2/11/2019: Tile and Plumbing completed. Waiting for the forms to be built and setup for the concrete foundation for the screen enclosure.
PRODUCTION DAY 11 - 1 MAR 2019

Forms set up for for the enclosure footer. I was surprised to only see boards on one side. Finally I can see how much room is around the pool and there is a lot less than what I had envisioned.

4 MAR 2019 - Termite treatment, city inspection, and window alarms approved.

Waiting for concrete footer to be poured.
PRODUCTION DAY 12 - 8 MAR 2019

Results of having boards only on one side. 
Concrete footer poured and hacked.
PRODUCTION DAY 13 - 11 MAR 2019

Concrete pad poured for the pool pump and the cracked sidewalk was replaced in the front.
PRODUCTION DAY 14 - 19 MAR 2019

Pavers delivered yesterday and the combing was started this afternoon. Looking good!
PRODUCTION DAY 15 - 20 MAR 2019

The combing was continued this morning. No work this afternoon. Looking good!
PRODUCTION DAY 16,17, & 18 - 25-27 MAR 2019

The combing grouting was completed and 90% of the pavers laid out. They didn't have enough pavers. Waiting for more to be produced and delivered. 
PRODUCTION DAY 19 - 03 APR 2019

STILL WAITING for more pavers to be produced, delivered, and installed. Ryan installed the pump, filters, heat pump, and salt-chlorine generator. Waiting for electricians. 
PRODUCTION DAY 20 - 08 APR 2019

The electricians installed the electrical service for the pool. Extreme Stucco removed the debris from next to the sidewalk and road. The pool company debris and excess concrete remains next to the pool.
PRODUCTION DAY 21/22 - 15/16 APR 2019; 96 days since ground was broken.

An 18 day delay was due to Extreme Stucco not ordering enough pavers for the job.

New pavers delivered and installed. Now waiting for the screened enclosure.